The Camp Perry Huts Project continued in November as workers finished assembling and wrapping exterior walls. Electrical contractors buried the remaining conduit to eventually supply power to the 21 huts. Trussed roof assemblies were fabricated n onsite using a template jig and flown into place via mobile crane. Hardie Plank siding will be added soon. Steel roofing material is expected soon. Once the huts are enclosed, the interior walls will receive moisture resistant drywall.